This project was for the Stage 5B raise the existing Mt Rawdon Tailings Storage Facility (TSF) from RL180m to RL181m.
The detailed requirement for the project included:
– The mobilisation and demobilisation for 12 number pieces of mine approved earthworks
– The establishment and disestablishment of project site facilities/services to mine site stand-
– The provision of management and supervision for the
– Approximately 0Ha of clearing for the borrow pits.
– Approximately 5,000m3 of topsoil stripping and stockpiling for borrow
– Removal and subsequent replacement of approximately 3,800m3 existing rock fill
– Removal and subsequent replacement of approximately 1,200m3 of road gravel
– Approximately 23,000m2 of existing surface scarification for subsequent
– Win, load, cart and place approximately 9,400m3 of clay
– Win, load, cart and place approximately 13,200m3 of general
– Win, load, cart and place approximately 7,000m3 of select rock
– Quality assurance testings of
– Borrow pit
In May 2022 McCosker returned to complete the construction of Stage 5D development (RL186.0m Lift) of the TSF. The RL186.0m Lift works comprise the following works:
– Lifts to the existing Northern, Southern and Western Embankments
– Construction of an Emergency Spillway at the north-western corner of the TSF
– Construction of the Stage 5D raise to the Decant Causeway at the south-western corner of the TSF, raising of a haul road along the western boundary of the TSF, Rock Fill Buttress construction for the Northern Embankment