BMA engaged McCosker to perform the preparation and infrastructure works for their incoming stacker reclaimers. This work involved the excavation, ground water treatment and cement stabilisation of approx. 24,000m 2 of crane pads.
The construction of an 8,000m 3 bund wall, installation of 24 x 1.2 / 0.9x14m deep concrete piles and associated concrete headstocks and the replacement of approx. 100 lineal metres of Stacker Reclaimer rail line. Due to the ever-changing ground conditions, McCosker were working constantly with the client to overcome schedule challenges which facilitated the delivery of an on-time and under budget project.